How minimum order quantities are set, how sample orders work, and the four parts of a lead time quote.
Brake and clutch parts are sold in cartons, not pieces, and that single fact explains most MOQ questions. This guide covers how MOQ is built, how to get samples, and how to read a lead time.
MOQ is normally a multiple of the packing quantity, not a commercial rule invented to raise order value. If a factory packs 20 pieces to a carton, an order of 10 pieces means opening a carton, repacking and re-labelling — which costs more than the extra 10 parts. Common drivers:
Ask which of these applies. "MOQ 100" because the carton holds 100 is negotiable in a way that "MOQ 100 because the die costs $4,000" is not.
For stocked parts, a sample is usually one piece at unit price plus courier. For made-to-order parts, expect a sample charge that is credited against the bulk order. What to confirm before paying:
A lead time of "25 days" hides four stages. Ask for the breakdown:
| Stage | What it covers |
|---|---|
| Production | Machining, assembly and testing after the order is confirmed and the deposit received. |
| Quality check | Pressure test, bore measurement, leak test, sampling of the batch. |
| Packing | Labelling, cartons, pallet or crate — custom packaging adds days. |
| Freight | Booking, trucking to port or airport, customs clearance at both ends. |
Production time usually starts when the deposit arrives, not when the PO is issued. If your schedule is tight, say so at the quotation stage — expediting is sometimes possible, but it is never free.
The more of this you send in the first message, the fewer round trips before you have a usable number.